Having imported two 900 MWe pressurized water reactors for the Daya Bay nuclear power plant, CGNPC engineers embarked on a development program that led to the CPR-1000 design. The first of these began operation at Ling Ao Phase II in September, while 16 are under construction and many more planned. A domestic supply chain has been built up with each project and now only about ten percent of components need to be imported.
By 2013, Zhang said, a further design evolution will clear certain areas of intellectual property retained by Areva, resulting in a Generation III design called the ACPR-1000 that CGNPC could market in other countries.
The current CPR-1000 design sits roughly between today's mainstream Generation II reactors and the latest Generation III units, with digital instrumentation and control systems and a design life of 60 years. Standard construction time is 52 months, and the unit cost for Chinese units so far has been under CNY 10,000 ($1500) per kilowatt
If you liked this article, please give it a quick review on ycombinator or StumbleUpon. Thanks
Featured articles
Ocean Floor Gold and Copper
Ocean Floor Mining Company